Planning

Production Planning

Production planning explained for small and midsized manufacturers: demand, master scheduling, materials, capacity and the planning cadence that keeps them aligned.

Production planning is the process of deciding what the plant will build, in what quantity, and in what order — far enough ahead that materials and capacity can be secured.

The planning layers

  • Demand plan — forecast plus firm orders, agreed with sales.
  • Master production schedule — what you intend to build, by period.
  • Material requirements planning — what to buy and make to support the MPS.
  • Capacity plan — whether the load fits the available hours.
  • Shop-floor schedule — the sequence for the next few days.

Cadence beats sophistication

A weekly planning meeting with the same agenda, the same reports and the same decisions being made in the same order will outperform a more advanced system with no rhythm.

Define what gets reviewed daily (exceptions and shortages), weekly (schedule and capacity) and monthly (demand and inventory policy).

Common failure modes

  • An MPS that is really just a list of everything sales wants.
  • No agreed time fence, so the schedule changes continuously.
  • Capacity checked only after materials are committed.
  • Planning done by one person with no documented method.